Installation guide

1 Installing rafter and battens:

  • Roof slope should be from 30º - 40º
  • Space between battens should be devided from the top in equal gauge of 290mm-350mm depends on roof slope and the kind of roof deck. The balance will be left for the lowest row.

2Installing main tiles:

  • Installing from the lowest row up to the top row
  • From right to left

3Installing other tiles and accessories: in the following order

  • Skylight tiles
  • Gable and gable end
  • Round ridge and round ridge end, round hip end
  • 3-way and 4-way round apex

4Finishing and cleaning the roof by ECO paint